ICR IAS JV

Category: Technowrap™ engineered composite repairs

Our client, an energy operator based in North America, faced a significant challenge with their main crude export line, which extended from a tank farm to a loading berth at sea. Erosion of the bitumastic coating at the transition zone had led to accelerated corrosion and isolated leaks had emerged, necessitating mechanical clamping. Further inspection revealed corrosion had progressed beneath the coating, resulting in substantial wall loss, particularly between the 5pm and 7pm positions on the pipe. Given the line’s critical nature and frequent use, a decision had to be made to address the issue without replacing the entire section of the pipe. 

To address our client’s challenge, our team opted for an engineered wrap solution at the transition zone. Two designs were developed – WTR 11280 for thin-wall sections and 11280 through-wall – aiming to provide a twenty-year life extension. The existing failing wrap and mechanical clamps were removed, and the pipe underwent preparation to SP 6 standards. Subsequently, four layers of the engineered wrap were applied to the thin-wall sections, while eight layers were applied to the through-wall areas. 

The execution of the project was carefully planned to coincide with windows between shipments when the line could be depressurized and de-inventoried, ensuring adherence to Health, Safety, and Environment (HSE) protocols. The initial scope of the project covered a 100-foot section of the pipeline. 

The implementation of the engineered wrap solution proved successful in mitigating the corrosion risks in the critical crude export line. The transition zone, once prone to erosion and accelerated corrosion, now boasts enhanced protection and a renewed structural integrity. The engineered wrap, with its thin-wall and through-wall designs, has provided a twenty-year life extension, meeting the client’s requirements for long-term reliability. 

This case study highlights the efficacy of our solution in addressing complex challenges in critical infrastructure, emphasizing the importance of tailored engineering interventions to extend the life of essential assets while minimizing downtime and ensuring environmental and operational safety.

Our client, an energy operator in the US, faced a significant challenge with the deteriorating condition of an offshore deck, primarily due to exposure to harsh environmental elements. The existing deck structure, originally constructed with bare steel, exhibited signs of wear, necessitating a solution that would not only address the current issues but also ensure long-term durability. The client’s key requirements included achieving a twenty-year life extension, minimizing downtime, eliminating hot works, and enhancing the overall aesthetics and safety of the deck. 

To meet our client’s challenge, we used our Technowrap™ engineered composite repairs solution to provide durable rehabilitation and extended service life. The process involved transforming the deck from bare steel to a fully covered, non-skid surface within days. 

The application of Technowrap™ was meticulously executed to ensure a seamless transition. The innovative system not only addressed the existing wear and tear, but also provided a robust protective layer against future environmental challenges. 

Crucially, the rehabilitation process was completed without any downtime for the operator, and the entire operation was carried out without resorting to hot works, ensuring a safe and efficient execution. 

The implementation of our Technowrap solution produced sustainable results: 

Twenty-year life extension: The deck rehabilitation successfully achieved the client’s objective of a twenty-year life extension, ensuring prolonged structural integrity and functionality. 

Efficient transformation: The transformation from a bare steel deck to a fully covered non-skid surface was accomplished within a few days, minimizing disruption to ongoing operations. 

No downtime or hot works: The rehabilitation process was conducted seamlessly without any operational downtime or the need for hot works, ensuring operator safety and environmental compliance. 

Aesthetically pleasing and weather-resistant: Three years post-rehabilitation, the deck not only retained its structural integrity, but also maintained an appealing appearance, standing up to the challenges posed by the elements. 

This case study highlights the successful application of our engineered composite repair solution, Technowrap™, in addressing complex challenges associated with offshore deck rehabilitation. The project’s positive outcomes underscore the effectiveness of advanced composite solutions in achieving long-term durability, safety, and aesthetic improvements in offshore infrastructure.

During routine flange maintenance work on a 16” transmission line, our client observed concerning issues with the protective bitumastic wrap. A subsequent inspection revealed the deterioration of the wrap and significant corrosion in the exposed area. Faced with the potential operational and environmental risks, it was essential that this was addressed immediately. 

To mitigate the corrosion risks and extend the life of the affected area, our team implemented an engineered composite wrap solution using WTR 12068. The pipe underwent meticulous preparation to SP 3 standards, ensuring a clean and suitable surface for the application. Eight layers of Technowrap, designed to provide enhanced protection, were applied to the compromised section of the 16” transmission line. 

The decision to opt for an engineered composite wrap aimed to provide a targeted and efficient solution, minimizing downtime and avoiding the need for a complete pipeline replacement. This approach also eliminated the necessity for hot works, ensuring a safer and more environmentally friendly execution. 

The outcomes of our intervention exceeded expectations, offering several key benefits to our client: 

Preservation of the Existing Line: The implementation of the engineered composite wrap successfully preserved the 16” transmission line, eliminating the need for a costly and time-consuming replacement. 

Elimination of Hot Works: The chosen solution avoided the use of hot works, mitigating safety risks and environmental concerns associated with traditional repair methods. 

Life Extension Achieved: The application of the engineered composite wrap, comprising eight layers of Tecnhowrap, provided a targeted five-year life extension to the affected area. This ensured the continued reliability and functionality of the transmission line. 

This case study underscores the effectiveness of strategic interventions in preserving the integrity of crucial infrastructure. By choosing an engineered composite wrap solution tailored to the specific challenges faced by the 16” transmission line, we successfully addressed the client’s concerns while delivering long-term benefits in terms of safety, efficiency, and operational continuity.

Client challenge

Several I-beam walkway supports faced severe corrosion issues, including through-wall penetration in both the flange and web sections, necessitating a restoration of their structural integrity. Our client needed a solution that avoided the high cost and unacceptable hot work associated with the like-for-like replacement of the supports.

What we did

Our approach involved providing an engineered design, implementing a Technowrap™ Structural Strengthening repair solution, and deploying trained personnel for the repairs. The repair design was meticulously crafted to withstand full applied loads, with a targeted design life of 20 years as per the client’s specifications. The complexity of the corroded beam areas required the use of a hand lay-up technique, as prefabricated plates were not feasible. ICR personnel underwent extensive training and testing at the Aberdeen headquarters, mastering various structural scenarios to ensure the effective application of repairs to intricate geometries.

Results

A Technowrap™ carbon fibre structural solution was successfully applied to the external surfaces of the supports, reinstating the integrity of the structure and the repairs were executed seamlessly while the platform remained in operation and production, eliminating the need for isolations, downtime, or platform shutdowns. The before-and-after visuals depict a notable transformation, showcasing the effectiveness of the implemented solution in restoring the I-beam walkway supports to their optimal condition.

Our team was tasked with addressing the severely corroded outer cladding of an accommodation module, with various areas identified as needing repair. The challenge included the need for both strengthening the cladding and creating a seal to prevent external environmental ingress.

Our scope of work involved the application of a composite repair solution to meet the dual requirements of strengthening and sealing. The chosen design incorporated one layer of Technowrap™ SRS for strength, complemented by a layer of Technocoat for sealing. The application process began with the preparation of the cladding’s outer surface to ST3 standards using grinding discs. The single layer of Technowrap™ SRS was then applied and compressed using rollers, with many repairs conducted off ropes to access various levels and challenging areas. The strategic scheduling of prep work avoided disturbances to personnel, considering specific time constraints, while safety concerns related to high winds and rain during rope access work were diligently managed.

The finalised repair, as seen in figure 3, delivered a durable solution for the severely corroded accommodation cladding, ensuring a design lifetime of 20 years. The strategic incorporation of rope access work led to substantial cost savings by obviating the necessity for extensive scaffolding. Beyond fortifying the overall structural integrity, the implemented solution revitalised water-damaged accommodation, contributing to an augmented Platform On Board (P.O.B) capacity. This not only addressed immediate concerns but also relieved pressure on bed space, exemplifying the successful execution of a comprehensive repair that underscored the efficiency of the approved design and application procedure.

Sections of a blast wall aboard a North Sea Platform were identified with severe wall loss and through-wall defects attributed to external corrosion. The structural integrity of the blast wall was compromised, necessitating a solution to address the corrosion-related challenges and reinstate its robustness.

We provided an engineered design calculation, Technowrap™ SRS materials, and deployed Rope Access trained technicians. The goal was to deliver a fully engineered repair that would effectively restore the integrity of the blast wall. The on-site construction of compression boards was crucial to achieving the required compression levels during the curing process. Following grit blasting, 15 bays, each measuring approximately 2 meters, were profiled using Technowrap™ FP. Subsequently, two layers of Technowrap™ SRS were applied, utilising the Technowrap™ DRS resin system to enhance impact resistance.

The repair of the blast wall on the North Sea Platform yielded significant results and benefits. The application of Technowrap™ SRS not only provided excellent corrosion resistance but also showcased its high strength capabilities, reinforcing the structural integrity of the blast wall. Despite the challenges, including severe wall loss and through-wall defects caused by external corrosion, the engineered design, in accordance with the original parameters, successfully reinstated the wall for an extended 20-year lifespan. The utilisation of Technowrap™ FP for profiling and the application of two layers of Technowrap™ SRS with the Technowrap™ DRS resin system ensured enhanced impact resistance. This comprehensive repair not only addressed immediate concerns but also positioned the blast wall to withstand future challenges, offering long-lasting structural resilience to the North Sea Platform.

The Valiant platform faced a critical structural issue as a tubular brace on the cellar deck suffered wall loss due to external corrosion, particularly at the intersection with a vertical column member. The integrity of the brace was compromised, necessitating a permanent repair to ensure its stability and functionality.

We undertook a comprehensive scope of work to address the client’s challenge. Our approach involved providing an engineered design calculation for a composite repair capable of withstanding the required loads. Additionally, Technowrap™ trained personnel were deployed to install the engineered repair, utilising the Technowrap™ PRS HP and Technowrap™ SRS composite repair system. The goal was to reinstate the integrity of the affected members.

The repair strategy focused on addressing not only stress levels in the corroded section but also the potential instability of the brace under compressive loads due to reduced stiffness in the corroded area. External factors, such as humidity from GMS Endurance, posed challenges during the repair installation, causing intermittent delays. The design for the 20-year lifetime repair was divided into two parts: Technowrap™ PRS HP applied axially on the diagonal brace and Technowrap Structural™ over the connection between the diagonal brace and the vertical cylindrical member.

Despite challenges posed by high humidity, our technicians efficiently utilised downtime by prepping required materials and, with OIM permission, worked overtime to ensure timely completion. The Technowrap™ composite repair was successfully installed, restoring the integrity of the tubular brace with a design lifetime of 20 years. The repair not only addressed the immediate concerns but also provided long-term structural reliability.

A North Sea platform faced a challenge requiring the upgrade of their GRP pipework sea water system. The project involved the replacement and installation of multiple GRP pipe spools, each with varying design conditions, including pressures up to 16 bar and temperatures up to 93ºC. In addition, our client required a 20-year lifetime design.

Our team carried out a comprehensive scope of work which included providing the necessary materials and deploying trained personnel for the fabrication and installation of the GRP pipework. Recognising the unique challenges posed by the project, we organised a specialised team capable of working on-site to fabricate and bond the pipe spools with minimal disruption to the platform.
The planning, fabrication, and installation phases were executed seamlessly, thanks to daily coordination and a dedicated team committed to meeting our client’s expectations.
The GRP pipe spools underwent construction, inspection, and release by a third party at ICR’s premises. Subsequently, the spools were transported offshore and installed by ICR technicians, who performed butt and wrap joints in situ. The establishment of a dedicated team and ongoing communication with the client played pivotal roles in the successful completion of this unique scope.

The project demonstrated remarkable success on multiple fronts. Firstly, the completion of the project without the requirement for hot work stands as a significant achievement, effectively minimising safety risks associated with such activities. Additionally, the implemented solution proved to be not only efficient but also highly cost-effective. Meeting the stringent criteria set by the client, the project successfully attained the 20-year design life requirement, ensuring long-term reliability. The undeniable success of the endeavor has not only met but exceeded client expectations, leading to an increased interest in ICR’s services, as evidenced by additional inquiries for broader scopes of work. This positive outcome underscores the client’s satisfaction and trust in ICR’s capabilities.

A North Sea platform faced a critical issue with its turbine hall roof, as water ingress was reported due to the corrosion of a previously fitted and edge-welded steel plate. This corrosion allowed water to penetrate, posing a threat to the turbine hall below.

We were tasked with providing a comprehensive solution to seal the roof and prevent further fluid ingress. The scope of our work involved devising an engineered design system utilising Technowrap™ DRS. This encompassed design calculations, selection of materials, and the installation process conducted by our trained personnel. The primary goal was to reinstate the integrity of the turbine hall roof.

Despite challenging weather conditions, successful weatherproofing enabled us to achieve the desired repair properties.

Overcoming the obstacle of turbines running below the repair area with a steel temperature of 65ºC was addressed by implementing a temporary shutdown.

Thorough surface preparation to Sa2.5, including grit blasting, ensured optimal adhesion for the two-layer Technowrap™ DRS repair system. To enhance safety, an orange nonslip paint was applied to the turbine roof post-repair.

The Technowrap™ DRS installation successfully restored the turbine roof’s integrity, ensuring a projected lifetime of 20 years.

The entire scope was delivered without any incidents, meeting and exceeding client expectations.

Our client, a global mining company based in Western Australia, faced a significant challenge with their coastal jetty piles. The structural steel piles exhibited extensive corrosion which drastically reduced their capacity and rendered the coastal jetty unusable for shipping mined products. In addition, the piles were coated with asbestos-containing material which required safe removal in order for adequate surface preparation for composite repairs. Furthermore, because of the coastal location, this presented significant challenges in terms of negotiating the tides and safely accessing the site.

To effectively address our client’s challenges, we implemented a comprehensive strategy which involved carrying out the following processes:

Safe Asbestos Coating Removal

We prioritised the safe removal of the asbestos-containing coating to ensure a secure environment for subsequent repairs.

Advanced Engineering Calculations

Utilising advanced engineering calculations, we minimised the surface preparation area required for composite repairs, optimising efficiency and reducing risks associated with asbestos exposure.

Rope Access Technicians

Overcoming access challenges posed by the coastal location, we deployed highly skilled rope access technicians working from suspended platforms. This approach ensured precise execution of repairs even in challenging conditions.

Our intervention yielded impressive results for the client by developing an innovative structural pile repair design methodology, specifically tailored to address the challenges posed by corroded piles. By leveraging advanced engineering calculations, we minimised the surface preparation area which reduced the risks associated with asbestos and enhanced overall project efficiency.

Our approach facilitated efficient repairs in areas with complicated geometry, ensuring seamless restoration of structural integrity. Beyond structural rehabilitation, our solution included comprehensive corrosion protection which distinguished it from traditional welded repairs that may remain susceptible to future corrosion. Additionally, our repairs successfully minimised the dead weight on the piles which helps to enhance structural stability and longevity.

In summary, our holistic approach not only addressed immediate structural challenges but also provided a sustainable and robust solution, ensuring the prolonged integrity of the coastal jetty piles.