Date | Client | Location |
---|---|---|
September 2022 | North Sea Transmission Line | UK |
Scope
There was potential for a through wall defect on a buried 2” NB valve coming off a 36” NB main import line. With excavation unable to take place prior to delivery of a mechanical clamp solution, the design had to cater for multiple potential valve orientations.
Solution
The mechanical clamp was designed to encapsulate the valve using a saddle and strongback assembly. The multi-part design enabled the clamp to enclose the valve, regardless of what position it was found to be in once excavated. 5-axis machined seal grooves were provided to ensure a reliable seal against the main 36” NB pipe, whilst keeping the size and weight of the solution as low as possible.
Design fully pressure tested in-house prior to shipping to client.
Results & Benefits
- Tested and verified clamp solution delivered to site in time for excavation date.
- Client had confidence a solution was on-site if required during excavation.
Featured articles
1 February | 2024
University of life stands Govan-raised engineer in good stead
5 December | 2023
LR and UKAS boost for ICR Group’s INSONO innovation
17 November | 2023